If a permit is obtained on May 1 and labor begins on May 11 with an estimated 15 days of required labor, how many float days are available for labor?

Prepare for the Virginia NASCLA Exam. Use flashcards and multiple-choice questions with hints and explanations to master the material. Ensure success with our resources!

To determine the number of float days available for labor, it is important to understand the timeline involved. A permit is obtained on May 1, which is the starting point from which any float days are calculated. Labor begins on May 11, which is 10 days after the permit is issued.

The estimated labor duration is 15 days. Therefore, if labor starts on May 11 and runs for 15 consecutive days, the labor would be projected to end on May 25 (11th to 25th counts as 15 days including the start day).

Now, to find the float days, we can look at the total period available from the permit date to the expected end of labor. From May 1 to May 25 is a total of 24 days. Since labor is estimated to take 15 days and begins 10 days after the permit is obtained, we subtract those 15 days of labor from the total of 24 days:

24 days (from May 1 to May 25) - 15 days (duration of labor) = 9 float days.

However, to accurately identify the float period relative to when labor starts, we focus on the fact that labor can potentially begin earlier than May 11.