Temporary erosion and sediment control measures must be removed within a maximum of how many days after final site stabilization?

Prepare for the Virginia NASCLA Exam. Use flashcards and multiple-choice questions with hints and explanations to master the material. Ensure success with our resources!

Temporary erosion and sediment control measures are essential during construction and land-disturbing activities to prevent sediment runoff and protect water quality. Once the site has reached a state of final stabilization—meaning that vegetation has been established or other permanent erosion controls are in place—there is a specified timeframe for removing these temporary measures.

The correct timeframe for removing temporary erosion and sediment control measures is within 30 days after final site stabilization. This period allows for the necessary assessment and ensures that the site has stabilized properly. It balances the need to maintain sediment control while also allowing for the site to transition to its final condition effectively. If the measures are left in place longer than 30 days, they can interfere with ongoing site operations and landscaping necessary for the project's completion.

Moreover, the specific regulation regarding this timeframe reflects best management practices aimed at minimizing environmental impact while ensuring compliance with erosion and sediment control guidelines. The other options reflect either shorter or longer timeframes that do not align with these established regulations.